NDPHC Rescues National Power Grid, Delivers 22 Sub-stations, Others

Related stories

Jubilation As FG Releases N50bn To Clear ASUU, Other Varsity Staff Allowances

By Kolawole Ojebisi The Minister of Education, Dr Maruf Alausa,...

Niger Gov. Backtracks On Deadlocks Ban Amid Public Outrage

By Kolawole Ojebisi Niger State Governor, Umar Bago, has revoked...

5 countries where $2,000 a month lets you retire in style

Have you ever daydreamed about sipping coffee by a...

Death of the Poor Pontiff Pope Francis

By Uzor Maxim Uzoatu The Vatican shocked the world when...

The Niger Delta Power Holding Company (NDPHC), a key intervention agency in the Nigeria’s power sector, has contributed over 3,400 megawatts (MW) to the national grid, delivering 22 substations since 2015, a new report has shown.

Through its six National Integrated Power Projects (NIPP) thermal power plants and scores of power substations, the company has been part of success story which saw the energy delivery capacity of national power grid hit 7,600MW currently.

The NIPP project report from 2015 to 2021 indicated that the NIPP programme is currently in its second phase that traverses transmission projects, distribution and renewable energy.

In the first phase, NDPHC which is owned by the three tiers of government kick-started the first phase of NIPP with the construction of 10 gas-fired power plants which it calls “The Big Ten” especially in the Niger Delta.

These projects have been essential to fast-tracking the development of the Nigerian power sector, tackling major problems, and meeting the NDPHC’s mandate of lighting the nation. From 2015 to 2021, several projects have been completed or ongoing with lots of progress recorded.

The company stated that the six NIPP power plants can now generate 3,400MW of electricity for the national grid, while the four other plants are still under construction even as some of their turbines operate partially.

NDPHC also said between 2015 to 2019, it has completed 2194 kilometres of 330 kilovolt (kV) and 887km 132kV transmission lines respectively. Also, the country now has 10 new 330/132kV Substations and eight 132/33kV substations connected to the national grid. These have added 5590MVA/330kV and 3493MVA/132kV capacity levels, respectively.

From June 2019 to January 2021, NDPHC’s transmission Department completed four new substations, boosting the national grid’s capacity further by 180MVA (Awka and Nkalagu Substations). While the Ihiala and Orlu GIS substations have been completed with a total of 120MVA capacity, the NDPHC had to wait for other associated projects to be completed, before the substations can be connected to the national grid. In terms of transmission, the NDPHC has made commendable progress, with all projects at an average of 80% completion.

Analysis of the report shows that the benefits of these projects are enormous as it has upscaled the nation’s reduction of Aggregate of Technical, Collection and Commercial Losses (ATC& C losses), Improved on Health, Safety and Environment (HSE) while incorporating safety valves and different layers of systems protective devices.

The other benefits are better cost recovery systems and Returns on Investment (RoI), inclusive growth and multi-sectoral Multiplier effects with positive impacts on the broad spectrum of a nation’s economy.

For renewable energy, the report said in order to key into the global drive of climate change and energy transition, NDPHC has also diversified its portfolio to include renewable energy to enhance its generation capacity.

The renewable energy department was recently created to facilitate NDPHC’s venture into power generation using on-grid and off-grid renewable energy sources to provide efficient, clean, affordable and universal access to electricity for more Nigerians, and meet the vision of renewables making 30% of the national energy mix by 2030 (Vision 30-30-30).

To this end, several projects have already been completed as at February 2021 and more of such projects are ongoing or upcoming as part of the Economic Sustainability Plan, Economic Growth Recovery Strategies and Re-Industrialization Agenda of the present administration.

In the gas sector, NIPP has a department dedicated to Fuel & Gas/Public Private Partnership (PPP) to manage all the gas pipeline projects of the company for its 10 power plants.

For electricity distribution, NIPP has completed over 360 injection substations with a combined capacity of about 3,540MW. It has also built about 2,600km of 11kV power distribution lines and 4600km of 33kV distribution lines which directly supply electricity to transformers in residential areas.
There have also been 296 Appropriated Distribution Projects which included injection substations, 1,924km of 33kV lines, 4600km of 11kV line, and other infrastructure.

According to the Managing Director of NDPHC, Mr Chiedu Ugbo, the company has also increased its distribution capacity with the installation of 25,900 Completely Self-Protected (CSP) transformers across the country.

He also said the company has done over 1000 intervention projects nationwide that include fixing vandalized or damaged power infrastructure while increasing the coverage area of power facilities.

The company said although there is progress in project delivery, there are challenges affecting some of these projects in the electricity market.

The major one is the theft of equipment and infrastructure, vandalism, lack of cooperation from Distribution Companies (DisCos).

The others are community issues regarding land and Right of Way (ROIs), vehicular accidents that have damaged some power infrastructure and the rising insecurity across facility areas,” it stated.

Commenting on the NDPHC report, a power sector advocate and President, Nigeria Consumer Protection Network (NCPN), Mr Kunle Kola Olubiyo, said: “In spite of all the tremendous milestone achievements by NIPP/NDPHC, there are major areas of impediments on the full realization of the lofty ideals of NIPP as championed by the management of NDPHC.”

Mr Olubiyo said some of these challenges include the delay in taking over projects by the DisCos’ in order to evade the burden of Capital Expenditure (CAPEX).
He also said the delay in Eligible Customers implementation should be cleared so that more heavy power users can benefit from the new NIPP assets.

Another challenge for the NDPHC is funding which, according to him, should be raised by the equity stakeholders (federal, state and local governments) for more power sector projects.

Mr Olubiyo also offered other quick-win solutions. “As part of the low hanging fruits and quick fixed solutions, there should be an upward review of NIPP GenCos’ tariff to bring it at par with other thermal plants in the country. At the moment, NIPP tariff is currently N20 per Kilowatts Hour (KWH) while other non-NIPP/NDPHC thermal GenCos’ tariff is N27KWH.”

He also called on the Nigerian Electricity Regulatory Commission (NERC) to fast track the valuation of NIPPs investment in transmission, distribution and gas infrastructure. That will enable NIPP/ NDPHC to recover over $3.5 billion investments in the power sector.

“The recovered sum will be reinvested in the power sector and that will again improve or close the infrastructural gap,” he noted.

Olubiyo who was a member of the National Technical Investigative Panel on Power Systems Collapses, Grid Stability And Reliability in June 2013, and a member, Presidential Adhoc Committee on Review of Electricity Tariff in Nigeria in August 2020, also said: “While NERC is working on the valuations, some amounts could be set aside from TCN as payments on account on the revenue derivable by TCN from investments by NDPHC/NIPP. This modality for cost recovery by NDPHC in the interim should be worked out as on-account payment or deposit on account pending conclusion of the valuation.”

He also said the same modality for the NIPP transmission assets applies to the DisCos.

“While NERC is working on the valuations, some amount could be set aside from each of the revenue/collections of the DisCos as payments on account as a way of re-couping the huge investment made by the NIPP at the downstream/distribution infrastructure. This can also be on – account payment or deposit on account pending conclusion of the evaluation,” said Olubiyo.

'Dotun Akintomide
'Dotun Akintomide
'Dotun Akintomide's journalism works intersect business, environment, politics and developmental issues. Among a number of local and international publications, his work has appeared in the New York Times. He's a winner of the National Youth Service Corps (NYSC) Award. Currently, the Online Editor at The New Diplomat, Akintomide has produced reports that uniquely spoke to Nigeria's experience on Climate Change issues. When Akintomide is not writing, volunteering or working on a media project, you can find him seeing beautiful sites like the sandy beaches that bedecked the Lagos coastline.

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from up to 5 devices at once

[tds_leads input_placeholder="Your email address" btn_horiz_align="content-horiz-center" pp_msg="SSd2ZSUyMHJlYWQlMjBhbmQlMjBhY2NlcHQlMjB0aGUlMjAlM0NhJTIwaHJlZiUzRCUyMiUyMyUyMiUzRVByaXZhY3klMjBQb2xpY3klM0MlMkZhJTNFLg==" pp_checkbox="yes" tdc_css="eyJhbGwiOnsibWFyZ2luLXRvcCI6IjMwIiwibWFyZ2luLWJvdHRvbSI6IjQwIiwiZGlzcGxheSI6IiJ9LCJwb3J0cmFpdCI6eyJtYXJnaW4tdG9wIjoiMTUiLCJtYXJnaW4tYm90dG9tIjoiMjUiLCJkaXNwbGF5IjoiIn0sInBvcnRyYWl0X21heF93aWR0aCI6MTAxOCwicG9ydHJhaXRfbWluX3dpZHRoIjo3NjgsImxhbmRzY2FwZSI6eyJtYXJnaW4tdG9wIjoiMjAiLCJtYXJnaW4tYm90dG9tIjoiMzAiLCJkaXNwbGF5IjoiIn0sImxhbmRzY2FwZV9tYXhfd2lkdGgiOjExNDAsImxhbmRzY2FwZV9taW5fd2lkdGgiOjEwMTksInBob25lIjp7Im1hcmdpbi10b3AiOiIyMCIsImRpc3BsYXkiOiIifSwicGhvbmVfbWF4X3dpZHRoIjo3Njd9" display="column" gap="eyJhbGwiOiIyMCIsInBvcnRyYWl0IjoiMTAiLCJsYW5kc2NhcGUiOiIxNSJ9" f_msg_font_family="downtown-sans-serif-font_global" f_input_font_family="downtown-sans-serif-font_global" f_btn_font_family="downtown-sans-serif-font_global" f_pp_font_family="downtown-serif-font_global" f_pp_font_size="eyJhbGwiOiIxNSIsInBvcnRyYWl0IjoiMTEifQ==" f_btn_font_weight="700" f_btn_font_size="eyJhbGwiOiIxMyIsInBvcnRyYWl0IjoiMTEifQ==" f_btn_font_transform="uppercase" btn_text="Unlock All" btn_bg="#000000" btn_padd="eyJhbGwiOiIxOCIsImxhbmRzY2FwZSI6IjE0IiwicG9ydHJhaXQiOiIxNCJ9" input_padd="eyJhbGwiOiIxNSIsImxhbmRzY2FwZSI6IjEyIiwicG9ydHJhaXQiOiIxMCJ9" pp_check_color_a="#000000" f_pp_font_weight="600" pp_check_square="#000000" msg_composer="" pp_check_color="rgba(0,0,0,0.56)" msg_succ_radius="0" msg_err_radius="0" input_border="1" f_unsub_font_family="downtown-sans-serif-font_global" f_msg_font_size="eyJhbGwiOiIxMyIsInBvcnRyYWl0IjoiMTIifQ==" f_input_font_size="eyJhbGwiOiIxNCIsInBvcnRyYWl0IjoiMTIifQ==" f_input_font_weight="500" f_msg_font_weight="500" f_unsub_font_weight="500"]

Latest stories

Latest News
Jubilation As FG Releases N50bn To Clear ASUU, Other Varsity Staff AllowancesNiger Gov. Backtracks On Deadlocks Ban Amid Public OutrageNiger State Governor Umaru Bago Orders Burnaboy, Jay-z, Faze, Victor Moses, Timaya, Solidstar, Rema, Others Arrested if Found in Niger State5 countries where $2,000 a month lets you retire in styleDeath of the Poor Pontiff Pope FrancisWhy was everything about Jesus made so controversial?Just In! Oborevwori, Deputy, Okowa, Manager, Others Dump PDP For APCAGF Vows To Look Into Petition Demanding Ex-NNPCL Boss Kyari's ProbeAlia To FG: Benue Needs Your 'Absolute Support', Not Emergency RuleEx-Governor Ortom Cancels 64th Birthday Celebration Amid Benue KillingsDetails As Finnish Court Approves Simon Ekpa’s Extradition to Nigeria, Sets Return Date for July 2025Oil Prices Stabilize on Short-Covering and an OPEC+ Output DeclineGood Governance and Development in Nigeria Compared to Some African and Global CountriesAlleged Misconduct: Ghana President Suspends S'Court Chief Justice As Investigation BeginsStop Casting Aspersions On N'ASS Based On Personal Frustrations, Senate Replies Bakare
X whatsapp