By Abiola Olawale
A Federal High Court sitting in Lagos has ordered major commercial banks to place a “Post No Debit” (PND) restriction on all accounts operated by the Osun State Government.
The interim freeze order, issued by Justice D.E. Osiagor under suit number FHC/L/CS/1233/2026, aims to preserve $13,924,343.32 and ₦157.5 million awarded to Gamji Nigeria Company Limited following a protracted legal and arbitration dispute over water infrastructure projects.
The legal showdown stems from two water supply and sanitation infrastructure contracts awarded to Gamji Nigeria Company Limited by the Osun State Government in June 2017.
The development focused on the Ilesa West Local Government Area, split into Slot 1 (construction of transmission mains and booster pump stations) and Slot 2 (water reservoirs), funded through an Islamic Development Bank loan facility facilitated via the Federal Ministry of Finance.
According to court filings presented by Gamji’s counsel, Yunus AbdulSalam (SAN), engineering design alterations, project scope variations, and fluctuating material and labor costs drove the original contract values upward—from an initial $15.98m to $20.24m for Slot 1, and from $9.70m to $10.95m for Slot 2.
Despite friction over price adjustments and extensions of time, the contractor achieved roughly 93% project completion by October 2023, earning a Substantial Completion Certificate issued by the state government on November 14, 2024.
However, disagreements over outstanding liabilities and escalation costs collapsed mediation efforts, triggering an arbitration notice served on April 3, 2025. Both parties participated in the proceedings, with the state government formally nominating its own arbitrator.
During court proceedings, Gamji said the projects were to be financed through a loan from the Islamic Development Bank, arranged by the Federal Ministry of Finance.
The company said the original contract value for Slot 1 was about $15.98m, while Slot 2 was valued at approximately $9.70m.
It alleged that changes to engineering designs, variations in the scope of work, and variation orders resulted in delays and increases in the contract values.
According to the affidavit, subsequent amendments raised the value of Slot 1 to about $20.24m and Slot 2 to approximately $10.95m.
Gamji further claimed that about 93 per cent of the work had been completed by October 2023 and that the state government issued a Substantial Completion Certificate on November 14, 2024.
The company said disagreements later arose over claims relating to extensions of time, price adjustments and increases in the cost of materials, labour and other inputs.
Gamji said it submitted several claims which were rejected by the state government, prompting attempts by the parties to resolve the dispute through mediation.
It said it subsequently issued an arbitration notice on April 3, 2025, while the state government accepted the arbitration process and nominated its arbitrator
The arbitration panel commenced proceedings, with a preliminary meeting held in Lagos on May 15, 2025.
According to Gamji, the panel delivered its final award on July 24, 2026, ordering the Osun State Government to pay $13,924,343.32 and N157.5m described as reimbursable arbitration fees.
The company also said the award provided for interest at 20 per cent per annum on any outstanding portion of the debt after the stipulated compliance period.
Gamji said the deadline for compliance expired on August 24, 2026, but that the awarded sums remained unpaid when it filed the court application.
Court order.
In the interim order, Justice Osiagor directed the listed financial institutions to place a “Post No Debit” restriction on the Osun State Government’s accounts maintained with them.
The judge ordered the preservation of funds up to the value of $13,924,343.32 and N157.5m towards the liquidation of the arbitral award, pending the hearing and determination of the motion on notice.
The order partly read: “That a preservation order of interim injunction is granted directing the cited financial institutions in Nigeria to immediately place a Post No Debit restriction on the Respondent’s account domiciled with them for the preservation of the funds with them for $13,924,343.32 … and N157,500,000.00 … towards the liquidation of the Arbitral Award dated 24th July, 2026 which has become due and enforceable; pending the hearing and determination of the motion on notice.”
The court adjourned the matter until October 22, 2026, for hearing of the motion on notice.