Borno Govt laments as Boko Haram stalls completion of N17bn roads, bridges

Hamilton Nwosa
Writer

Ad

2027: INEC Boss, Yakubu Warns, Says APC, ADC, PDP, LP, Others, violating electoral laws with early campaigns

By Abiola Olawale The Chairman of the Independent National Electoral Commission (INEC), Professor Mahmood Yakubu, has sounded a warning to Nigeria's political parties, declaring that early political campaigns by aspirants and parties pose a severe threat to the nation's fragile democratic framework. Speaking at a high-level stakeholders' roundtable on the challenges of early political campaigns,…

MDBs set to scale up $137bn climate finance push at COP30 in Brazil

By Obinna Uballa Multilateral development banks (MDBs) are preparing to expand climate financing commitments at COP30 in Belém, Brazil, building on a record $137 billion deployed in 2024, according to the Joint Report on Multilateral Development Banks’ Climate Finance made available to New Diplomat on Wednesday. The report, coordinated by the European Investment Bank (EIB)…

Concerns as Qatar Tightens Visa Rules, Bars Nigerian Men from Solo Travel

By Abiola Olawale The Qatari government has announced its decision to bar Nigerian men from travelling solo to the country. The Qatari Ministry of Interior said the new visa regulations for Nigerian men travellers came after recent cases of overstays. Under the new policy, Nigerian men must show intent to travel with their wives, sisters,…

Ad

Borno State Government on Thursday decried the negative effects of the activities of the Boko Haram insurgency in the state was the inability to complete N17 billion roads and bridges projects in Maiduguri metropolis, including three-kilometre Lagos Street Bridge awarded in 2012.

The insurgents, according to government officials had targeted roads construction workers especially engineers and the routes through which building materials were transported to various projects sites in the state.

The roads projects cover a total distance of 48 kilometres, including the Old Maiduguri 7.5 kilometer dual carriage way.

Commissioner of Works and Transport, Alhaji Adamu Lawan disclosed this at the Maiduguri-Bulumkutu and Lagos Street project sites, while briefing newsmen over the uncompleted roads projects.

The affected construction firms, according to him; include Eighteenth Engineering Company, EEC, Grand Scope Company and a Kano-based Hajaig Construction Company handling the Bulumkutu roads projects that had been stalled by insurgency and insecurity of engineers and other workers.

He said, “The non-completion of these roads and bridges in Maiduguri in metropolis was caused by the insurgency. We are very frustrated over this development. It prevented the haulage of roads construction materials and equipment to sites; while the lives of sites engineers were threatened, including the killings of some contracting partners in 2013 and 2014 at three different project sites in Borno State.

“Hajaig firm had; for example, brought in its laterite from Damboa, 87 kilometres from Maiduguri, unfortunately the road was closed to motorists for almost two years ago. Other roads construction equipment had to be transported from far away Kano to this Bulumkutu project site. The state government had wanted to revoke this contract, but doing so could lead to the loss of over N2 billion.”

He however said the Bulumkutu high density community roads complex had reached 98 per cent completion, explaining that the remaining two per cent, included roads’ marking and painting.