Borno Govt laments as Boko Haram stalls completion of N17bn roads, bridges

Hamilton Nwosa
Writer

Ad

Tinubu’s defence minister Badaru quits over deteriorating health, amid rising insecurity

By Obinna Uballa Nigeria’s Minister of Defence, Alhaji Mohammed Badaru Abubakar, has tendered his resignation, bringing an abrupt end to his tenure amid concerns over his worsening health. The development was confirmed on Monday by the President’s Special Adviser on Information and Strategy, Bayo Onanuga, who disclosed that President Bola Tinubu has accepted the resignation.…

BEYOND BOOTS ON THE GROUND

By Dakuku Peterside Not long ago, a well-worn phrase began to echo again in Nigeria’s public conversation: “We need more boots on the ground.” It is a phrase that sounds decisive, almost comforting. It suggests movement, resolve, and visible action. In a country where too many communities live under the shadow of fear, the image…

(PHOTOS) Ayuk, Ajetomobi, Orokpo Join Oni for 11th Annual ‘Prayer Storm’ in Port Harcourt

A powerful coalition of charismatic leaders, including the President of The Men of Issachar Vision, Pastor Samson Ajetomobi, and the fiery Apostolic voice, Apostle Michael Orokpo, is set to descend on Port Harcourt this January for the 11th Annual edition of "Prayer Storm." The highly anticipated spiritual convergence will take place from Monday, January 12th,…

Ad

Borno State Government on Thursday decried the negative effects of the activities of the Boko Haram insurgency in the state was the inability to complete N17 billion roads and bridges projects in Maiduguri metropolis, including three-kilometre Lagos Street Bridge awarded in 2012.

The insurgents, according to government officials had targeted roads construction workers especially engineers and the routes through which building materials were transported to various projects sites in the state.

The roads projects cover a total distance of 48 kilometres, including the Old Maiduguri 7.5 kilometer dual carriage way.

Commissioner of Works and Transport, Alhaji Adamu Lawan disclosed this at the Maiduguri-Bulumkutu and Lagos Street project sites, while briefing newsmen over the uncompleted roads projects.

The affected construction firms, according to him; include Eighteenth Engineering Company, EEC, Grand Scope Company and a Kano-based Hajaig Construction Company handling the Bulumkutu roads projects that had been stalled by insurgency and insecurity of engineers and other workers.

He said, “The non-completion of these roads and bridges in Maiduguri in metropolis was caused by the insurgency. We are very frustrated over this development. It prevented the haulage of roads construction materials and equipment to sites; while the lives of sites engineers were threatened, including the killings of some contracting partners in 2013 and 2014 at three different project sites in Borno State.

“Hajaig firm had; for example, brought in its laterite from Damboa, 87 kilometres from Maiduguri, unfortunately the road was closed to motorists for almost two years ago. Other roads construction equipment had to be transported from far away Kano to this Bulumkutu project site. The state government had wanted to revoke this contract, but doing so could lead to the loss of over N2 billion.”

He however said the Bulumkutu high density community roads complex had reached 98 per cent completion, explaining that the remaining two per cent, included roads’ marking and painting.