Borno Govt laments as Boko Haram stalls completion of N17bn roads, bridges

Hamilton Nwosa
Writer

Ad

It’s a long haul, by Hakeem Baba-Ahmed

By Hakeem Baba-Ahmed   A lot has happened since US President Donald Trump’s outburst against what he called our disgraced country. He had threatened to take steps to protect Nigeria’s Christian population which he said is a victim of genocide. All options were on the table, from our classification as a Country of Particular Concern…

(FULL LIST) Super Eagles Coach Unveils 54-man Provisional Squad List Ahead of 2025 AFCON

By Abiola Olawale Super Eagles Head Coach, Eric Chelle, on Tuesday unveiled Nigeria’s provisional squad for the 2025 Africa Cup of Nations (AFCON). Victor Boniface, Ola Aina, Francis Uzoho, and Kelechi Iheanacho were among notable returnees on the provisional list. A breakdown of the squad shows that they are six goalkeepers, 13 defenders, 12 midfielders,…

Osun PDP Conducts Primary Election as Adebayo Adedamola Clinches Ticket After Adeleke’s Exit

By Abiola Olawale The Peoples Democratic Party (PDP) in Osun State has concluded its governorship primary election, electing Adebayo Olugbenga Adedamola as the party's candidate for the upcoming August 8, 2026, gubernatorial election. The primary, held in Osogbo on Tuesday, December 2, 2025, proceeded despite an internal crisis and the formal resignation of one of…

Ad

Borno State Government on Thursday decried the negative effects of the activities of the Boko Haram insurgency in the state was the inability to complete N17 billion roads and bridges projects in Maiduguri metropolis, including three-kilometre Lagos Street Bridge awarded in 2012.

The insurgents, according to government officials had targeted roads construction workers especially engineers and the routes through which building materials were transported to various projects sites in the state.

The roads projects cover a total distance of 48 kilometres, including the Old Maiduguri 7.5 kilometer dual carriage way.

Commissioner of Works and Transport, Alhaji Adamu Lawan disclosed this at the Maiduguri-Bulumkutu and Lagos Street project sites, while briefing newsmen over the uncompleted roads projects.

The affected construction firms, according to him; include Eighteenth Engineering Company, EEC, Grand Scope Company and a Kano-based Hajaig Construction Company handling the Bulumkutu roads projects that had been stalled by insurgency and insecurity of engineers and other workers.

He said, “The non-completion of these roads and bridges in Maiduguri in metropolis was caused by the insurgency. We are very frustrated over this development. It prevented the haulage of roads construction materials and equipment to sites; while the lives of sites engineers were threatened, including the killings of some contracting partners in 2013 and 2014 at three different project sites in Borno State.

“Hajaig firm had; for example, brought in its laterite from Damboa, 87 kilometres from Maiduguri, unfortunately the road was closed to motorists for almost two years ago. Other roads construction equipment had to be transported from far away Kano to this Bulumkutu project site. The state government had wanted to revoke this contract, but doing so could lead to the loss of over N2 billion.”

He however said the Bulumkutu high density community roads complex had reached 98 per cent completion, explaining that the remaining two per cent, included roads’ marking and painting.