Minister Directs Early Completion Of Zungeru Power Plant

Hamilton Nwosa
Writer
Zungeru power plant

Ad

Is Nigeria cursed, or are we the curse?

The past 10 days in Nigeria have witnessed unprecedented negative news, a level of chaos, insecurity, and institutional decay that should trouble the conscience of all the leaders. Our country is now going through troubling times, not by fate, but by our collective leadership failures that allow insecurity, lawlessness, and institutional decay to thrive. Each…

Worsening Insecurity: Five policemen killed in Bauchi, Boko Haram abducts 12 women in Borno

...Tinubu pulls 100,000 policemen from VIPs in frantic effort to curb menace By Obinna Uballa Nigeria’s worsening security crisis continued over the weekend, with multiple attacks in some states, leaving five policemen dead, several communities traumatised, and at least 12 women abducted by suspected Boko Haram insurgents in Borno State. The violence unfolded amid renewed…

Concern as audit uncovers N61bn financial breaches in NNPCL under Kyari, flags 28 major irregularities

By Obinna Uballa The Office of the Auditor-General for the Federation has uncovered more than N61 billion in questionable transactions involving the Nigerian National Petroleum Company Limited (NNPCL), revealing a sweeping pattern of financial breaches, unverified expenditures and violations of federal regulations across the national oil company and its subsidiaries. The concerning findings are contained…

Ad

The Minister of Power, Mr Abubakar Aliyu, has directed the early completion of the Zungeru Power Plant in Niger State.

Mr Odutayo Oluseyi, Assistant Director Press, Ministry of Power, made this known in a statement in Abuja on Friday.

Aliyu spoke while receiving the consultants and contractors, Messrs. CNEEC-Sinohydro consortium in charge of Engineering, Procurement and Construction (EPC) of 700 Mega Watts, Zungeru Hydroelectric Power Project.

The minister assured the contractors of the Federal Government’s resolve to surmount the challenges faced by the contractors in the discharge of their duties.

He said that the challenges bother on Security, COVID 19, cost adjustment owing to the extra work outside the contracted sum and the delay in release of funds by China Exim Bank.

Aliyu further informed the contractors of efforts of the ministry of power, through the Ministry of Finance, at resolving the issue of opening of the escrow account in a commercial bank.

“Prescribed in the Subsidiary Loan Agreement with Exim bank of China which negates the current policy of Government which transferred Government accounts in all the commercial banks to the Treasury Single Account (TSA),” he said.

Aliyu expressed satisfaction with the presentation made by the contractors and encouraged them to meet the Dec 28 deadline of completing the project.

He also assured them of addressing all constraints that may hinder the delivery of the project.
Speaking earlier during his presentation, the project Director, Dr. JBO Adewumi of Coyne et Bellier (Tractebel) / Decrown Consultancy Service, said the assessed overall percentage of completion of the project is about 90%.

He pleaded for quick resolution of the constraints enumerated.
The Zungeru hydro power plant project is located on Kaduna River, 8 kilometer upstream of the confluence with the Gumna River in Rafi Local Government Area of Niger State.

This is approximately 20 km northeast of Zungeru, 25km southeast of Tegina, 43km northwest of Minna and 77km downstream of the Shiroro power Plant. (NAN)